PMP Change Request Flow: Exact Sequence
- Authors

- Name
- passpmpnow
PMP exam loves this. This is one of the highest-leverage things to memorize.
Change Request Flow (Exact Sequence)
- Identify the change
- Analyze impact (cost, schedule, risk, quality, scope)
- Submit formal change request
- CCB reviews and decides
- Update baselines / plans (if approved)
- Communicate decision to stakeholders
- Implement the approved change
- Update lessons learned
Most common exam trap
Team member applies the change before the CCB reviews it.
Correct behavior: always process change through the formal system.
If question gives you 2 correct choices
- choose the one with “analysis first”
- not the one that jumps to “approve / implement”