Why It’s Important

Every PMP question that mentions “variance” or “deviation” secretly tests your understanding of baseline vs actual.

  • Baseline = approved plan
  • Actual = real performance data

Typical Confusions

TermMeaning
Cost BaselineTime-phased budget (what we plan to spend)
Actual Cost (AC)What we really spent
Schedule BaselineApproved project timeline
Actual DatesWhat actually happened

Variance = Actual – Baseline.


Exam Example

Earned value = 50,000,ActualCost=50,000, Actual Cost = 60,000.
Is the project under or over budget?

✅ Over budget (AC > EV). Baseline comparison drives performance evaluation.


Integration Connection

You can’t change a baseline unless you go through Integrated Change Control.
That means — a new baseline = an approved change request.