Baseline vs Actual — Why PMP Loves This Pair
- Authors

- Name
- passpmpnow
Why It’s Important
Every PMP question that mentions “variance” or “deviation” secretly tests your understanding of baseline vs actual.
- Baseline = approved plan
- Actual = real performance data
Typical Confusions
| Term | Meaning |
|---|---|
| Cost Baseline | Time-phased budget (what we plan to spend) |
| Actual Cost (AC) | What we really spent |
| Schedule Baseline | Approved project timeline |
| Actual Dates | What actually happened |
Variance = Actual – Baseline.
Exam Example
Earned value = 60,000.
Is the project under or over budget?
✅ Over budget (AC > EV). Baseline comparison drives performance evaluation.
Integration Connection
You can’t change a baseline unless you go through Integrated Change Control.
That means — a new baseline = an approved change request.